Calculator
SPI compares earned progress with planned progress.
SPI formula
SPI = EV ÷ PVAn SPI of 1.00 means earned progress equals planned progress at the status date. Below 1.00 is behind plan; above 1.00 is ahead in earned-value terms.
SPI is not a duration ratio
Traditional SPI is expressed in budgeted value, so it should not be read as a direct promise that a project will finish a specific percentage early or late. For forecasting cost, some EAC scenarios combine CPI and SPI when both cost and schedule performance are assumed to influence the remaining work.
See the Schedule Variance Calculator for the currency-value difference between EV and PV.