Project controls calculator

Estimate at Completion Calculator

Compare EAC forecasts for temporary variance, continuing CPI, combined CPI × SPI, and your own bottom-up ETC.

EAC scenario calculator

Compare forecasts under different assumptions instead of using one formula blindly.

Methodology note. Formulas are based on established Earned Value Management terminology. Core references include Project Management Institute (PMI) educational resources and U.S. Department of Energy EVM guidance. Last reviewed: August 14, 2026. Read methodology · View sources

There is more than one EAC formula

The correct EAC approach depends on the forecast assumption. If past variance is considered atypical, remaining work may be budgeted at the original rate. If current cost efficiency is expected to continue, BAC ÷ CPI is commonly used. If both cost and schedule performance are expected to influence the remaining work, CPI and SPI can be combined. A credible new bottom-up ETC can also replace index-based forecasting.

Temporary variance

EAC = AC + (BAC − EV)

Current cost efficiency continues

EAC = BAC ÷ CPI

Cost and schedule performance continue

EAC = AC + (BAC − EV) ÷ (CPI × SPI)

Bottom-up forecast

EAC = AC + ETC

Once you choose a forecast, calculate ETC, VAC and TCPI against the relevant target.