Earned Value Management · Free project controls tool

Earned Value Calculator

Measure cost and schedule performance, compare forecast-at-completion scenarios, and see the efficiency required to recover your project budget.

No signupRuns in your browserFormula sources published

Project performance inputs

Enter the four core EVM values. Add a bottom-up ETC only if you have one.

Total performance budget at completion.
Budgeted value planned by the status date.
Budgeted value of work actually completed.
Actual cost incurred for completed work.
Your independent forecast of remaining cost.
Ratios are currency-independent.

One calculation, several decisions

See performance, forecast the finish, test recovery

EVM combines budget, progress and actual cost. The calculator turns those inputs into performance indices, variances and completion forecasts.

1. Measure performance

CPI shows cost efficiency and SPI shows schedule efficiency relative to the plan.

CPI = EV ÷ AC

2. Forecast total cost

Compare EAC scenarios instead of relying on one formula without understanding its assumption.

EAC depends on assumption

3. Test recoverability

TCPI estimates the efficiency required on the remaining work to hit BAC or a revised target.

TCPI = work left ÷ money left

What the four core inputs mean

The quality of the result depends on using values from the same status date and baseline.

BAC
The authorized performance budget for the work in scope at project completion. Management reserve is tracked separately from the performance measurement baseline.
PV
The budgeted value of work planned to be completed by the status date.
EV
The budgeted value of work actually accomplished by the status date.
AC
The actual cost incurred for the work performed by the status date.
Methodology note. Formulas are based on established Earned Value Management terminology. Core references include Project Management Institute (PMI) educational resources and U.S. Department of Energy EVM guidance. Last reviewed: August 14, 2026. Read methodology · View sources

Worked example

Suppose BAC is $1.25M, planned value is $525k, earned value is $475k and actual cost is $520k.

Performance

CPI = 0.91. The project is earning about $0.91 of budgeted value for each $1.00 spent.

SPI = 0.90. Earned progress is behind planned progress at the status date.

Forecast

If current cost efficiency continues, EAC is approximately BAC ÷ CPI. The result is higher than BAC, producing a negative VAC.

The recovery panel then compares current CPI with the TCPI required to protect the original BAC.

Frequently asked questions

What does a CPI below 1.0 mean?

It indicates unfavorable cost efficiency: the earned value of completed work is lower than the actual cost incurred.

What does an SPI below 1.0 mean?

It indicates earned progress is behind planned progress at the status date. Traditional SPI should not be interpreted as a direct time-duration forecast.

Why does the calculator show several EAC values?

Because each EAC formula embeds a different assumption about future performance. Comparing scenarios is more informative than treating one equation as universally correct.

Does BAC include management reserve?

In standard EVMS usage, management reserve is outside the performance measurement baseline and is not included in BAC. It can be part of a broader contract budget base.

Is EarnedValueCalc affiliated with PMI?

No. EarnedValueCalc is an independent educational tool and is not affiliated with, endorsed by or sponsored by Project Management Institute.